In an effort to reduce the campus’s carbon footprint, a two-megawatt solar parking canopy will be built at the East Remote Parking Lot. The new solar photovoltaic system will project two-megawatts of power (off-setting approximately 20% of the PG&E campus power demand).
The campus must install and test equipment at Slug Substation for the new solar photovoltaic system. In order to complete this work a campus power shut-down is required. On March 21 and March 28, campus power will be shut-down to install all the required equipment to connect the photovoltaic system to the campus grid and perform testing.
Shutdowns
- Saturday, March 21st from 4 a.m. to 11:59 p.m.
- Saturday, March 28th from 4 a.m. to 11:59 p.m.
Please power down your computers, printers, equipment, etc. before the power outage.
Also please note elevators will not be operational during these power outages.
Review the following four lists for the status of your building and check with your Building Coordinator for additional information:
A. Facilities that will experience utility power interruptions March 21st and March 28th.
B. These facilities are planned to be unaffected by the March 21st and March 28th utility interruptions because Cogen will be providing power.
C. Facilities with emergency and standby power supplied by generators.
D. Facilities that are planned to be unaffected by the utility interruptions because fed directly from PG&E.
Please email questions to Nathan Weiner (UCSC Project Manager) naweiner@ucsc.edu.
A. The following facilities will experience utility power service interruptions:
Saturday, March 21st from 4 a.m. to 11:59 p.m.
Saturday, March 28th from 4 a.m. to 11:59 p.m.
- Antenna Site (KZSC + Wireless Tenants)
- ARC Center
- Baskin Visual Arts
- Baytree Bookstore
- Biomedical Sciences
- Camper Park
- Chadwick Garden
- Classroom Units
- College Nine and Ten Dining
- College Nine and Academic, Apartments
- College Ten/Soc. Sci. 2 and Academic, Apartments
- Core West Parking
- Cowell College, Apartments
- Crown College and Apartments
- Digital Arts Research Center
- Engineering 2
- Farm, Agro Ecology, Quarry Village
- Grad Student Housing
- Grad Student Commons / IVETA
- Hahn Student Services
- Housing Services / Visual Arts Research Facility
- Humanities
- Kerr Hall
- McHenry Library
- Merrill College and Apartments
- Music Facility
- Natural Science Wood Shop
- Oakes College/Apartments
- P. E. Fitness Center
- Physical Sciences Building
- Porter College
- Porter / Kresge Apartments
- Quarry Village (Areas A, B, C, D, E, F)
- Rachel Carson Academic, Dining, Commons, Dorms, Apartments
- Redwood Grove Apartments
- Redwood Building
- Stevenson College
- Student Union
- Theater Arts Complex
- University House
- Upper Quarry Amphitheater
- West Field House
B. The facilities below are planned to be unaffected by the utility service interruptions because Cogen will be providing power.
- Baskin Engineering
- Center for Adaptive Optics
- Central Heat Plant
- Communications
- Cowell Student Health Center
- Earth & Marine Science
- East Field House
- Engineering Auditorium
- Fackler Cogeneration
- Fire Station
- Interdisciplinary Science
- Natural Science 2
- Science Library
- Sinsheimer
- Thimann
C. Facilities with emergency and standby power supplied by generators that are planned to be operating during the power outage. Standby and Emergency power distribution provided by generators is planned to operate in the same manner as during previous power service interruptions.
- Bay Tree Bookstore
- Biomedical Sciences
- Classroom Units
- College 9 (Soc Sci 1)
- College 9 Apartments
- College 9/10 Dining Hall
- College 9/10 Dorms
- College 10 (Soc Sci 2)
- Core West Parking Structure
- Cowell College
- Cowell Infill Apartments
- Crown/Merrill Colleges
- Crown/Merrill Apts – Lower and Upper
- Digital Arts Research Center
- Engineering 2
- Hahn Student Services
- Humanities
- Kerr Hall
- Kresge College
- McHenry Library
- Music Facility
- Oakes College
- Physical Science Building
- Porter College, Kitchen & Dining
- Porter/Kresge Infill Apartments
- Rachel Carson Admin/Academic
- Rachel Carson Apartments
- Rachel Carson Dorms A, B, C, D
- Rachel Carson Kitchen
- Stevenson College
- Stevenson Infill Apartments
- Theatre Arts Complex
- Upper Quarry Amphitheater
- West Field House
D. Facilities that are planned to be unaffected by the utility service interruptions because fed directly from PG&E. (Lower Campus, Coastal Science Campus, 2300 Delaware and all leased facilities)
- Coastal Science Campus
- Faculty & Staff Housing
- 2300 Delaware
- Arboretum
- Cardiff House Annex
- Granary
- Cardiff House
- Blacksmith Shop
- Carriage House
- Family Student Housing
- Emergency Response Center/Police Station
- Water Tank Pump Station
- Physical Plant Shop Stores
- Ranchview Terrace
- Hazardous Waste Facility
- Hay Barn
- Barn-H/Receiving/Risk Services
- Barn-G
- Physical Plant Trailers Near Corp Yard
- PP&C Trailers West of Barn-G
- Physical Plant Paint, Sign & Bug Shop
- Fleet Services
- Cook House
- Barn Theater
- Main Kiosk