Temporary Road Closure of Upper Heller

To: UCSC Community

From: Larry Pageler, Director of Transportation and Parking Services (TAPS)

On Monday, August 11, 2014, construction crews will begin roadway repair work on the North Heller bridge, located between Engineering Loop to the south and Porter-Kresge Road to the north. During this phase of the Campus Road Rehabilitation Project the bridge will be closed and traffic destined for the North Remote Parking Lot and the Camper Park will be re-routed to Porter-Kresge Road. This detour is expected to be in place for approximately one week, with an anticipated completion date of Friday, August 15, 2014.

Questions about the 2014 Road Rehabilitation Project should be directed to Damon Adlao, Project Manager with Physical Plant, at 459-2338.